AC HV Withstand Test of 150 kV Extention GIS – PLTU Palabuhan Ratu

Lokasi Pekerjaan : PLTU Palabuhan Ratu
Obyek Pekerjaan : 150 kV of Extention GIS
Lingkup Pekerjaan : AC HV Withstand Test of 150 kV Extention GIS.
Tangaal : September, 2014.
Statu Pekerjaan : Instalasi Baru
ratu1

ratu2

Spesifikasi GIS  :
a.Location : PLTU Palabuhan Ratu
b.Substation name : 150 kV Extention GIS
c.Manufacture : Xian XD Switchgear Electric CO.Ltd
d.Model / Type : ZF9-252
e.Rated max Voltage : 252 kV
f.Nominal Current : 3150 Amper
g.Frequency : 50 HZ

HV Test Equipment Spesification :
Merk : Hipotronic Variable Reactor
Model : 7300 – 600 Sr.
Rating : 0 – 300 kV, 600 kVA max
Tuning Range : 1000 pF Min – 21.000 pF Max
Frequency : 50 Hz
Rated current : 2 A

PT. Prima Power

Jl.Bukit Cinere Raya No.148D
Depok 16512
T : 021-7536073- F : +6021-7536401
pt.primapower@yahoo.com

SERVICES

Jasa Pemeliharaan & Instalasi Tenaga Listrik

Jasa Pengujian Tegangan Tinggi

Tenaga Out Sourcing

Pengadaan Barang dan Jasa

Perlengkapan Kami

NEWS

blog_thumb
Cleaning & Maintenance Kubikel 20 kV – Group Pasar Kemis – Tangerang
blog_thumb
Induce Test AC HV Transformator Tenaga 10.5/70 kV – PLTU Bolok
blog_thumb
Pemeliharaan Peralatan Listrik di Bekasi Power